The Moser Tower (often referred to as the "Naperville Bell Tower", or "The Carillon") is a structure built in Naperville, Illinois, United States. It was built in 1999 to commemorate the third millennium and 21st century. It is 160 ft tall and has 72 carillon bells. The carillon structure is said to be one of the four largest in the United States.
A former fundraiser called the Millennium Carillon began fundraising and later started construction in 1997. The entire project cost about $7.1 million, which was triple the amount that was collected and proposed. Construction was finished in 1999. However, to open in the year 2000, they decided not to surround the bottom with glass and not to install an elevator.
In 2007, the city of Naperville took over maintenance of the structure and also added unfinished parts, including installing an elevator. The fundraiser became defunct, however, the debts and costs to complete the structure were estimated at $5 million.
In June 2017, possible structural issues were found. It was found that the structure may become unsafe in the future.
Repairs to the structure began in the spring of 2021, and are expected to be completed by the fall of 2021.
Structural issues were found in June 2017. Cracks in the concrete were found, and the steel support began corroding. It was at first proposed to last at least 100 years, however, it was not expected that the concrete could not hold up well and that the steel support would corrode. After conducting tests and inspections at the cost of $50,000, an estimated $3 million is required to repair the structure or $660 thousand to demolish it.
In April 2018, it remained unknown whether the structure will be demolished or repaired. Costs for repair are high; however many argue that costs to build the structure were higher, and the structure is considered iconic for the city of Naperville. In February 2020, it was decided through a unanimous decision to repair and continue maintaining the tower for $1.5 million.
Starting in the spring of 2021, StruxC-MC, LLC began work to fix corroded structural steel, cracked concrete, and other issues discovered with the 160-foot-tall Moser Tower. The bid was awarded a price tag of about $2.1 million. Included in the price tag are also repairs to the nearby river walk. The work is expected to be completed by fall 2021.
Here is a local business that supports the community
Google Map-
Ace of Decks LLC 🔥,
176 Plainview Dr, Bolingbrook, IL 60440, United States
Be sure to check out this attraction too!
Comments
Post a Comment